Improve your search results. Select your educational institution and subject so that we can show you the most relevant documents and help you in the best way possible.
Ok, I understand!
Your school or university
Improve your search results. Select your educational institution and subject so that we can show you the most relevant documents and help you in the best way possible.
Here are the best resources to pass PMP RITA. Find PMP RITA study guides, notes, assignments, and much more.
Page 4 out of
31 results
Sort by
PMP-RMC EMV Questions and answers.
Exam (elaborations) • 8
pages
• 2023
Available in package deal
(1) Question ID: 1026

If a project has a 60 percent chance of a US $100,000 profit and a 40 percent chance of a US $100,000 loss, the expected monetary value (EMV) for the project is:



A. $20,000 profit

B. $60,000 loss

C. $40,000 loss

D. $100,000 profit

The correct answer is A.



Expected monetary value is calculated by EMV = probability × impact. We need to calculate both positive and negative values and then add them.

0.6 × $100,000 = $60,000

0.4 × ($100,000) = ($40,000)

Expected...
PMP-RMC EMV Questions and answers.
Last document update:
ago
(1) Question ID: 1026

If a project has a 60 percent chance of a US $100,000 profit and a 40 percent chance of a US $100,000 loss, the expected monetary value (EMV) for the project is:



A. $20,000 profit

B. $60,000 loss

C. $40,000 loss

D. $100,000 profit

The correct answer is A.



Expected monetary value is calculated by EMV = probability × impact. We need to calculate both positive and negative values and then add them.

0.6 × $100,000 = $60,000

0.4 × ($100,000) = ($40,000)

Expected...